Building disputes

Legal avenues for resolving building disputes are leaving consumers out of pocket. We look at your rights and options.

Pencil and ruler on house plan

Whether you’re paying for minor alterations or building your dream home, you’ll probably get good odds on something going pear-shaped.

That’s not the worst of it. If you’ve had substandard work done, your options for getting it fixed are limited – unless you’ve got deep pockets.

Your rights

When things go wrong with building work, there are 2 main laws that can help you.

The Consumer Guarantees Act (CGA) requires work done by tradespeople to be carried out with reasonable skill and competence. If it’s not, the CGA says you can ask the person who did the job to fix it at no cost to you. If they can’t or won’t fix it, then you can employ someone else and claim the cost from the original tradesperson.

The CGA applies to services provided by the building industry but not to buildings and building materials – they’re covered by the Building Act.

The Building Act requires tradespeople to provide warranties that work will be done competently using suitable materials. These warranties form part of every contract for residential building work, regardless of whether the contract refers to the warranties or not, and apply for 10 years.

In addition, the act contains a specific 12-month defect repair period. If the homeowner finds defects within 12 months of the completion date, the builder must fix them or prove they’re not responsible.

Enforcing your rights

It’s when it comes to enforcing your rights that things get tricky. There are industry bodies that’ll investigate complaints about their members but many tradespeople don’t belong to these bodies. So where next?

Adjudication

This is an option if a dispute arises under a construction contract. The Construction Contracts Act 2002 introduced a formal process for adjudicating on building disputes. The act covers all types of construction work – from building a home to altering or decorating one.

If you go down this route, a qualified and independent adjudicator looks at the issues and makes a decision on what should be done. The process is designed to be relatively quick: you should have a decision within 25 working days.

However, it can be costly. Parties to the dispute have to pay the adjudicator’s costs. These can vary hugely – from several thousand dollars to tens of thousands – depending on the scale and complexity of the dispute. On top of this, you’ll have to meet any other costs you incur, such as legal fees.

You and the other parties can agree who will act as the adjudicator. If there’s no agreement, there’s a process for having an adjudicator selected – but you may be charged a fee ($400 to $500) for this.

Mediation and arbitration

These are other forms of dispute resolution that can be used to resolve problems arising under a construction contract. But unlike adjudication, which is a statutory process, you and the tradesperson must agree on using these options and also agree on the mediator/arbitrator.

At $2000 to $4000 a day, mediation is cheaper than arbitration. But there’s no guarantee you’ll get a resolution: the mediator’s role is to facilitate discussion, not make a decision. You’ll get a binding decision from arbitration but you’ll also pay more: arbitration can cost tens of thousands of dollars.

Disputes Tribunal

The Disputes Tribunal is an option for relatively minor matters. As Barry and Marian Wilson found (see "Case studies"), cases involving complex issues about how a floor is laid might not be dealt with easily.

Another drawback is the tribunal can only hear claims up to $15,000 – or up to $20,000 if both parties agree. For many disputes, this will be far too low.

Weathertight Homes Tribunal

Owners of leaky homes can take their case to the Weathertight Homes Tribunal. The tribunal deals with claims on dwellings built or altered within the previous 10 years.

Making a claim can be a complex business – and you’ll likely need a lawyer. In one recent case, the successful claimants’ legal costs were estimated at $60,000.

The tribunal has limited power to award costs so the expense of hiring expert help may have to come out of your own pocket.

Court action

Going to court is your last resort. Ministry of Justice figures show there are long waiting times for civil hearings. In the High Court, it could take up to a year for your case to be heard.

Legal costs are also high: the expense involved in taking a civil action can be out of proportion to the scale of the dispute.

Building Practitioners Board

You can complain to the Building Practitioners Board if a licensed builder has done a substandard job. Builders must be licensed – or supervised by someone who is – if they’re doing restricted building work. However, the board can only discipline the builder – it can’t order reparation.

Industry schemes

Building guarantees can offer some redress if things go wrong. The two major building trade organisations – the Certified Builders Association and the Registered Master Builders Association – offer these guarantees for work done by their members. Several insurers also provide guarantees, but they’ll need to vet the builder and project before work starts.

They cover loss of deposit, defects and non-completion of work (although only up to set limits). There are also a number of exclusions under each guarantee.

Home warranty insurance

Across the Tasman, home warranty insurance is compulsory (except in Tasmania) but it’s been problematic. The Australian system requires builders to take out insurance for all residential building projects; the homeowner is the beneficiary of the insurance policy. However, in all states except Queensland it acts as “last resort” insurance, which means consumers can only make a claim if the builder is dead or insolvent (or has disappeared).

Queensland rules

This proviso doesn’t apply in Queensland, which has “first resort” insurance. The state’s consumers can claim for losses arising from non-completion or shoddy work regardless of whether the builder is alive, dead or otherwise missing in action.

For any residential building work over a set value, builders in the state are required to obtain insurance from a statutory body called the Building Services Authority (BSA).

Queensland’s system is government-backed and is seen as offering much higher levels of protection than in other states, where private insurers provide cover.

As well as running the insurance scheme, the BSA is responsible for disputes resolution and builder licensing. Builders in the state must be licensed to carry out work valued over $1100. Licence fees and other fees for service fund the BSA.

Among its powers, the BSA can require defective or incomplete building work to be remedied. If the contractor fails to do this, insurance cover kicks in and the authority will pay to remedy any outstanding problems.

If the BSA has to pay out, it can pursue the contractor for costs and also has the power to prosecute – fines of up to $25,000 are possible.

We think Queensland’s system has merit.

Australia’s experience with home warranty insurance shows it needs to be government-backed. An Australian senate inquiry in 2008 found private insurers didn’t want to participate in a first resort scheme because they considered the risks too high. The same report described the “last resort” insurance offered by private insurers as so minimal that it shouldn’t be called insurance.

Our view

  • If you suspect there’s a problem, you need to act quickly – ideally before work has been signed off. It’ll be cheaper and faster if you can sort issues out informally. But this won’t always be possible.

  • We’d like to see a disputes body similar to Queensland’s Building Services Authority to eliminate the maze of tribunals, schemes and courts that Kiwi consumers have to navigate. Building wrangles are often complex and technical. There should be a specialist body to deal with them.

  • Builders should also be required to take out insurance for all residential building work. A government-backed “first resort” scheme would offer better protection for consumers than last resort options.

Barry and Marian's case

Barry and Marian's case

Barry and Marian's case

Barry and Marian Wilson paid $10,000 to have laminate flooring installed in their house. They had the flooring laid in their living areas and also (on the advice of the installer) in the bathroom.

Soon after, ridges appeared in the flooring caused by the boards pushing together. The couple also discovered the product shouldn’t have been installed in the bathroom as it was unsuitable for wet areas.

The Wilsons went to the Disputes Tribunal to try to get things fixed. It took over a year and numerous hearings before a decision was made. During this time, the ridges in the floor got worse.

Barry and Marian eventually got some compensation but were left unhappy with both the outcome and the process. Appealing the decision to the District Court would have meant hiring a lawyer – an expense they just couldn’t wear.

Pete and Gill’s case

Pete and Gill’s case

Pete and Gill’s case

Pete and Gill (not their real names) wanted new weatherboards, windows and doors put in their Wellington home. When the doors and windows arrived, the couple found two different types and shades of timber had been used for the internal framing.

So they went to the Disputes Tribunal and, after two hearings, got the joinery company to replace the timber. The company also had to repair leaks in the door.

Pete and Gill then ended up in the Tribunal again over a dispute with the builder who had installed the doors and completed the other building work.

The couple believed the work was substandard; the building expert they hired agreed. So they got another builder to fix the worst of the problems. The original builder then took them to the Tribunal over non-payment of his bill.

The Tribunal referee decided Pete and Gill should have given the first builder more time to remedy the problems.Under the Consumer Guarantees Act, the supplier must be given the opportunity to make good. It’s only when the person can’t or won’t that you can seek redress.

Pete and Gill weren’t happy with the decision – they believed they’d given the builder plenty of time to fix things – but couldn’t afford to take the case further.

Got a problem?

Got a problem?

16jun assert your rights clp need more help promo default

Got a problem?

The Consumer Advice Line is available to all our members for support on any consumer-related issue. Our expert advisers can explain your rights and help you resolve problems with a retailer.

Contact us now

Member comments

Get access to comment

Sheryl A.
14 Jun 2019
Case studies

I cannot find any case studies?

Consumer staff
14 Jun 2019
Re: Case studies

Hi Sheryl,

You can find our case studies at the bottom of this article ("Barry and Marian's case" and "Pete and Gill's case").

Kind regards,

Natalie - Consumer NZ staff.